  We centered big foot in the holes as much as we could using our layout string. But the string couldn't stay there while shoveling the earth back in, and we needed a way to keep the sonabube from shifting when we started to backfill.

so we lined up some 2x4s on either side, and then staked them on either side as much as we could. Then we screwed in some perpendicular pieces of scrap to keep the sonatube from shiting left to right. It worked like a charm.