  Day 11

We got a late start today because we expected rain, but when it didn't materialize, we went out at noonish.

Today's task is to fill the holes with 2+ inches of gravel, put in the footings with sonatube and backfill the holes.

Jonnie & Nathan removing loose dirt at the bottom of the holes before filling with gravel.

Thems are big holes to fill: 4 feet deep and around 3 feet in diameter. We hit bedrock all over the place except for one.